New Tap and Meter Box Directions
White flag must be installed at the proposed location within 24 hours before BRRWC can obtain required locates to dig onsite.
BRRWC reserves the right to move the proposed location for the water tap if any of the below list requirements are not met without further notice to the customer.
Taps and Meter box requirements
All meter box location must be off of county or state right of ways.
All meter box locations must maintain a three foot radius clear of:
- Power Poles
- Utility Boxes
- Trees
- Shrubs
- Storm or Culvert Pipe
- Catch Basins
- Driveways
- Mailboxes
- Flower Beds
All grading work must be complete within 3 inches of final grade.
All drive way(s) must be clearly marked.
All property lines must be clearly marked.
All stumps must be removed.
The above requirements not only apply to the proposed location of the meter box, but also to the location directly across the road from the meter location, when digging to tap the water main.
BRRWC will smooth the site and seed / straw the site. BRRWC will not replace mulch or sod on the site.